Monthly Archives: September 2011

KODIAK DIESEL-PLANT STACK REPLACEMENT

The stacks at our Main Diesel Plant are getting a facelift! Our Power Generation mechanics began the process in August by replacing the old rusty stack on Diesel Unit #1, the oldest of the four units, with a shiny new … Continue reading

Posted in Maintenance Work

More Wind in Our “Sales”

More Wind in Our “Sales” The KEA High Penetration Wind Project Darron Scott PRESIDENT/CEO REPORT KEA is officially moving forward with adding three more wind turbines on Pillar Mountain. The KEA Board of Directors authorized the purchase through approval of … Continue reading

Posted in Pillar Mountain Wind Farm